Rig #2
A. Workover/Completion Rig – Evertson International Rig #2
1998
Hopper model GXXTA, totally remanufactured by OEM to API specifications. All
supporting documentation will be supplied before rig inspection. Includes
260,000#, 102’ Hopper four-legged mast; new safety ladder-climbing device;
six-line crown and block with 1" drilling line; separate hydraulic system
for tongs and winch, powered by a 60 h.p. electric motor; sand drum with
16,000’ of 9/16" sandline; hydromatic brake; Crown-O-Matic; new GM8V92T
motor rated at 500 h.p.; new Allison 6061 6-speed automatic transmission; new
6,000# hydraulic winch with 0.50" line; tubing board capable of racking
12,000’ of 3.50" tubing or drillpipe, 8,000’ of 4.50" tubing,
or 6,000’ of 5.50" tubing; new Clincher tubing tongs, slips, and
handling tools for 2.375", 2.875", 3.50", 4.50", and
5.50" tubing; all tongs, elevators, and handling equipment for rods from
0.75" thru 1.25"; new 14’x12’ working floor with all safety
handrails, ladders, slide, and stairs; catwalk with safety handrails and
ladder; two sets of pipe racks;
B. Pump and Circulating Equipment
New Gardner-Denver model TGH triplex pump, rated at 500 h.p.,
powered by new GM8V92T motor, rated at 475 h.p. with either 4" or 5"
liners. Complete with new hydraulic-powered 5"x6" centrifugal
charging pump and suction manifold for multiple intakes. Skid-mounted unit.
150 bbl., three-compartment mud tank with stairs and handrails. All hardline,
chiksans, bails, hoses, and manifold rated to at least 5,000 psi. and tested
to 5,000 psi. All come with 2" Weco 1502 unions to prevent mis-matched
unions. Pump/choke manifold is five valve system with rated at 5,000 psi. with
2" Halliburton 10,000 psi. valves and 2" 5,000 psi. adjustable choke
with air/hydraulic test pump with recording chart for testing BOP’s and
manifold. Manifold is securely mounted on steel rig-up pad.
C. Generator House/Tool Room/Supply Room/Shop
12’x40’ skid-mounted metal building with electric
powered air compressor, arc welding equipment, oxy/acetylene welding and
cutting equipment, spare parts and consumables storage, work bench with vise,
tool storage, new high pressure steamer/washer with sufficient high-pressure
steam hose to reach all equipment on location. New Cat 210 kW generator,
powered by new Cat 3406 motor installed within house. Proper electrical
connections in a covered box to operate entire rig and camp. New Perkins 150
kW standby generator, skid-mounted, that plugs into power grid of generator
house with safety switching between the two generators.
D. BOP and Accumulator
Remanufactured Hydril ‘GK’ annular BOP with new Reedy
three-station, 40- gallon accumulator with 80 gallon oil reservoir, charged
with Cat 56 triplex pump powered by 20 h.p. explosion-proof electric motor and
50:1 air/hydraulic back up system. Skid mounted with overhead beams and mount
for BOP.
|